Aipu solids control as a professional solid control system manufacture and drilling waste management unit manufacture, we could not only provide you the best and high quality products for meet your demands in oil drilling fields, but also provide full after sale service. Today Aipu machinery will share some practical tips about how to install mud cleaner, which is important solid control equipment for your whole solid control system.
Installation and debugging of mud cleaner
1. We should pay attention to the pipeline and flow direction when installing mud cleaner.
2. Before installation, the station must be stable or directly installed on ground. Use expansion bolt to fix pedestal on cement base station. Station is made of concrete, the plane size is circular or square. The height of base station is 150mm.
3. It’s better to leave the operation space for management in the plane layout. Since no moving parts during working, we don’t need to maintain this equipment. But need to keep stable load at entrance, evenly opening and closing drain valve to avoid man-made damage.
The tips about mud cleaner installation and debugging
1. Prohibit to dismantle mud cleaner without any permits.
2. In general, mud cleaner should be installed after deep well water pump.
3. Before solids control system stop working for a long time, add appropriate corrosion inhibitor to water, and adopt full water moisture measures to reduce corrosion, protect system.